Beginning the week of July 7, 2025, Northwoods Excavating, Inc. of Thetford, VT will install a new, larger culvert at the low point of Kate Wallace Road. The project is expected to be completed by the end of July 2025.
The planned work includes:
-Construction of a temporary road (Phase 1 – the road will be shifted upstream)
-Excavation and setting (by crane) of the outlet end of the 6′ x 6′ precast box culvert
-Construction of a temporary road (Phase 2 – the road will be shifted downstream)
-Excavation and setting (by crane) of the inlet end of the 6′ x 6′ precast box culvert
-Installation of new guardrail, cleanup, seeding & mulching
Kate Wallace Road will remain open to vehicles during construction. However, drivers should expect occasional short delays, especially during the setting of the box culvert and guardrail installation. The contractor will notify residents in advance of any road closures.
NOTE: Emergency services will take precedence over any temporary road closures. Please call the Public Works Department at 802-649-2209 with any questions. Thank you for your patience and cooperation during this important project.